Earlier this month Giraudo said in an interview with TuttoSport that the reconstruction of Delle Alpi is highly uncertain in several points. The plans are to remodel it for at least a 40 000 capacity arena, however the deal they have signed is only valid if they build a 35 000 capacity arena. Moreover, the commercial plan, building restaurants and other activity centers around the new arena is for now not included.
Giraudo also said that no company has been contracted to start with the building. If by middle of July the work has not begun they will postpone the project to Christmas, and would it not work out at that time as well, then it will be postponed to next year. Reconstructing Delle Alpi is estimated to take 24 months to complete.